INCREASING POWER OUTPUT AND FLEXIBILITY OF KOPS I HIGH HEAD POWER PLANT WITH THE HELP OF WATERHAMMER SIMULATIONS

Stefan Höller-Litzlhammer, Helmut Jaberg, Bernhard Wittwer

Publikation: Beitrag in Buch/Bericht/KonferenzbandBeitrag in einem KonferenzbandBegutachtung

Abstract

With highly volatile loads in electric grids from renewables like wind and solar grid service tasks become more and more important. A chance to increase the annual turnover of a storage hydro power plant is found not only in increasing the power output but also the availability and flexibility of an existing power plant. With the help of modern techniques in waterhammer simulations in combination with sophisticated numerical models for complex hydro power plant components an increase of power output and flexibility at the same time could be identified.
Originalspracheenglisch
Titel20. Internationales Seminar Wasserkraftanlagen
Untertitel40 Jahre Engagement zwischen Industrie und Wissenschaft - eine Erfolgsgeschichte
Herausgeber (Verlag)Technische Universität Wien
Seiten599-609
Seitenumfang11
ISBN (Print)978-3-9504338-1-4
PublikationsstatusVeröffentlicht - 16 Nov. 2018
Veranstaltung20. Internationales Seminar Wasserkraftanlagen - Wien, Österreich
Dauer: 14 Nov. 201816 Nov. 2018

Konferenz

Konferenz20. Internationales Seminar Wasserkraftanlagen
KurztitelVienna Hydro 2018
Land/GebietÖsterreich
OrtWien
Zeitraum14/11/1816/11/18

Fields of Expertise

  • Sustainable Systems

Treatment code (Nähere Zuordnung)

  • Experimental
  • Application
  • Theoretical

Fingerprint

Untersuchen Sie die Forschungsthemen von „INCREASING POWER OUTPUT AND FLEXIBILITY OF KOPS I HIGH HEAD POWER PLANT WITH THE HELP OF WATERHAMMER SIMULATIONS“. Zusammen bilden sie einen einzigartigen Fingerprint.

Dieses zitieren