Due to liberalization of the european electricity market, the high voltage grids are more and more stressed by international transits. Superposing national loadflows, the n-1-criteria may be reached in parts of the grid. Within this research project different aspects of congestion management are analysed. Remedial measures in the grid like installation of FACTS are covered as well as redispatch of power generation.
StatusFinished
Effective start/end date1/01/0231/01/08