The 880 MW pumped storage hydro power plant Gouvães, part of the Alto Tâmega hydro power scheme from Iberdrola is currently under construction in the north of Portugal. The energy storage and grid regulating plant is equipped with 4 reversible Francis pump turbines with nominal power of 220 MW and a gross head of 660 m, the discharge in turbine mode is 160 m³/s and in pumping mode 128 m³/s. The current paper underlines the layout, the design criteria and the results of the physical small-scale test of the tail race surge tank in the hydraulic laboratory. Most unfavourable load cases were studied such as synchronous pump trip in resonance and multiple loading and unloading followed by full load rejection in generating mode. A collaborated transient investigation for water hammer and mass oscillation capturing was conducted and gives cross checking opportunity.
Originalsprache | englisch |
---|---|
Titel | 20th International Seminar on Hydropower Plant |
Redakteure/-innen | Eduard Doujak, Christian Bauer |
Seiten | 841-850 |
Publikationsstatus | Veröffentlicht - 2018 |
Veranstaltung | 20th International Seminar on Hydropower Plants - , Österreich Dauer: 14 Nov. 2018 → 16 Nov. 2018 https://www.viennahydro.com/ |
Konferenz
Konferenz | 20th International Seminar on Hydropower Plants |
---|---|
Kurztitel | Viennahydro |
Land/Gebiet | Österreich |
Zeitraum | 14/11/18 → 16/11/18 |
Internetadresse |
Fingerprint
Untersuchen Sie die Forschungsthemen von „HYDRAULICS OF THE TAIL RACE SURGE TANK OF GOUVÃES PUMPED-STORAGE HYDROPOWER“. Zusammen bilden sie einen einzigartigen Fingerprint.Projekte
- 1 Abgeschlossen
-
Gouvaes Hydropower - Gouvaes Pumpspeicherkraftwerk Portugal
1/01/17 → 31/12/17
Projekt: Forschungsprojekt